Building Permit
Inspections cannot currently be scheduled for this permit (226735) because its status is set to "FINALLED" instead of "ACTIVE". Please contact support.
Permit Number
226735
Status
FINALLED
Issued
9/21/2016
Permit Type
SFR-ADDITION
Zone
R1-10 PRD ESL
Address
APN
212-01-343
Subdivision
PINNACLE PEAK COUNTRY CLUB UNIT FIVE
Lot Number
9
Air Cond
663 Sq Ft
Covered
617 Sq Ft
Owner
MEYER FAMILY TRUST
Responsible
MEYER FAMILY TRUST
Builder
MTO CONSTRUCTION
Valuation
$150,482.92
| 3 FOOTING/EXTERIOR | ||
| Status | APPROVED | |
| Last Scheduled | 04/25/2017 | |
| Last Inspected | 04/25/2017 | |
| 4 STEM | ||
| Status | APPROVED | |
| Last Scheduled | 04/25/2017 | |
| Last Inspected | 04/25/2017 | |
| 5 PLUMBING/UNDERGROUND | ||
| Status | APPROVED | |
| Last Scheduled | 12/11/2017 | |
| Last Inspected | 12/11/2017 | |
| 6 FOOTING/INTERIOR | ||
| Status | APPROVED | |
| Last Scheduled | 05/08/2017 | |
| Last Inspected | 05/08/2017 | |
| 7 WATER/UNDERGROUND | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 8 WATER SERVICE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 9 SEWER | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 10 ELECTRIC/UNDERGROUND | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 11 MASONRY GROUT | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 12 BOND BEAM | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 14 ROOF NAIL | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 15 ROUGH PLUMBING | ||
| Status | APPROVED | |
| Last Scheduled | 12/05/2017 | |
| Last Inspected | 12/05/2017 | |
| 16 ROUGH ELECTRIC | ||
| Status | APPROVED | |
| Last Scheduled | 10/10/2017 | |
| Last Inspected | 10/10/2017 | |
| 17 ROUGH MECHANICAL | ||
| Status | APPROVED | |
| Last Scheduled | 10/10/2017 | |
| Last Inspected | 10/10/2017 | |
| 18 ROUGH FRAME & INSULATION | ||
| Status | APPROVED | |
| Last Scheduled | 10/16/2017 | |
| Last Inspected | 10/16/2017 | |
| 19 WALLBOARD | ||
| Status | APPROVED | |
| Last Scheduled | 10/19/2017 | |
| Last Inspected | 10/19/2017 | |
| 20 EXTERIOR FOAM AND LATH | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 21 NATURAL GAS LINE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 22 PROPANE GAS LINE | ||
| Status | APPROVED | |
| Last Scheduled | 12/11/2017 | |
| Last Inspected | 12/11/2017 | |
| 24 TEMP ELEC/PERM POSITION | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 25 TEMP CERTIFICATE/OCCUPANCY | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 26 FINAL BUILDING | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 27 FINAL ELECTRIC | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 28 FINAL MECHANICAL | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 29 FINAL PLUMBING | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 31 FINAL SITE | ||
| Status | APPROVED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 32 TEMPORARY ON-SITE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 33 LOWEST FLOOR | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 35 MISCELLANEOUS FOOTINGS | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 36 TEMP C/O FIRE INSPECTION | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 38 FENCE FTG | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 39 FENCE FINAL | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 40 RETAINING WALL FOOTING | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 41 RETAINING WALL FINAL | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 42 PRE SITE | ||
| Status | APPROVED | |
| Last Scheduled | 02/27/2017 | |
| Last Inspected | 02/27/2017 | |
| 43 FINAL OFFSITE PUBLIC WORKS | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 03/30/2018 | |
| Last Inspected | 03/30/2018 | |
| 46 CONSTRUCTION MEETING | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 06/01/2017 | |
| Last Inspected | 06/01/2017 | |