Building Permit
Inspections cannot currently be scheduled for this permit (259332) because its status is set to "FINALLED" instead of "ACTIVE". Please contact support.
Permit Number
259332
Status
FINALLED
Issued
2/25/2020
Permit Type
SFR-CUSTOM IN SUBDIVISION
Zone
R1-7 ESL
Address
APN
176-14-481
Subdivision
EAGLE RIDGE AT FOUNTAIN HILLS
Lot Size
38451 Sq Ft
Lot Number
6
Air Cond
5281 Sq Ft
Covered
3283 Sq Ft
Owner
PICASSO HOMES AND DEV. INC
Responsible
PICASSO HOMES AND DEV. INC
Builder
PICASSO HOMES AND DEV. INC
Valuation
$950,677.59
|
CertOcc_259332.pdf (145 KB) |
|
IECC Certification (114 KB) |
|
Setback Certification (39 KB) |
|
Setback Certification (39 KB) |
|
Setback Certification (39 KB) |
|
Setback Certification (39 KB) |
|
Air Balance Testing (332 KB) |
|
Field Change - Engineering Working Doc (400 KB) |
|
Field Change - Engineering Working Doc (400 KB) |
|
Field Change - Engineering Working Doc (400 KB) |
|
Field Change - Engineering Working Doc (400 KB) |
|
Field Change - Engineering Working Doc (400 KB) |
|
Setback Certification (39 KB) |
|
Setback Certification (39 KB) |
|
Permit_259332.pdf (37 KB) |
|
SitePlan_ 259332 (2 MB) |
| 3 FOOTING/EXTERIOR | ||
| Status | APPROVED | |
| Last Scheduled | 06/30/2021 | |
| Last Inspected | 06/30/2021 | |
| 4 STEM | ||
| Status | APPROVED | |
| Last Scheduled | 08/02/2021 | |
| Last Inspected | 08/02/2021 | |
| 5 PLUMBING/UNDERGROUND | ||
| Status | APPROVED | |
| Last Scheduled | 11/01/2021 | |
| Last Inspected | 11/01/2021 | |
| 6 FOOTING/INTERIOR | ||
| Status | APPROVED | |
| Last Scheduled | 12/06/2021 | |
| Last Inspected | 12/06/2021 | |
| 7 WATER/UNDERGROUND | ||
| Status | APPROVED | |
| Last Scheduled | 11/01/2021 | |
| Last Inspected | 11/01/2021 | |
| 8 WATER SERVICE | ||
| Status | APPROVED | |
| Last Scheduled | 10/21/2021 | |
| Last Inspected | 10/21/2021 | |
| 9 SEWER | ||
| Status | APPROVED | |
| Last Scheduled | 11/01/2021 | |
| Last Inspected | 11/01/2021 | |
| 10 ELECTRIC/UNDERGROUND | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 11 MASONRY GROUT | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 12 BOND BEAM | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 13 PUBLIC WORKS TEMPORARY C OF O | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 14 ROOF NAIL | ||
| Status | APPROVED | |
| Last Scheduled | 05/16/2022 | |
| Last Inspected | 05/16/2022 | |
| 15 ROUGH PLUMBING | ||
| Status | APPROVED | |
| Last Scheduled | 09/09/2022 | |
| Last Inspected | 09/09/2022 | |
| 16 ROUGH ELECTRIC | ||
| Status | APPROVED | |
| Last Scheduled | 06/23/2022 | |
| Last Inspected | 06/23/2022 | |
| 17 ROUGH MECHANICAL | ||
| Status | APPROVED | |
| Last Scheduled | 06/23/2022 | |
| Last Inspected | 06/23/2022 | |
| 18 ROUGH FRAME & INSULATION | ||
| Status | APPROVED | |
| Last Scheduled | 06/27/2022 | |
| Last Inspected | 06/27/2022 | |
| 19 WALLBOARD | ||
| Status | APPROVED | |
| Last Scheduled | 07/12/2022 | |
| Last Inspected | 07/12/2022 | |
| 20 EXTERIOR FOAM AND LATH | ||
| Status | APPROVED | |
| Last Scheduled | 06/08/2022 | |
| Last Inspected | 06/08/2022 | |
| 21 NATURAL GAS LINE | ||
| Status | APPROVED | |
| Last Scheduled | 12/07/2022 | |
| Last Inspected | 12/07/2022 | |
| 22 PROPANE GAS LINE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 24 TEMP ELEC/PERM POSITION | ||
| Status | APPROVED | |
| Last Scheduled | 11/05/2021 | |
| Last Inspected | 11/05/2021 | |
| 25 TEMP CERTIFICATE/OCCUPANCY | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 26 FINAL BUILDING | ||
| Status | APPROVED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 27 FINAL ELECTRIC | ||
| Status | APPROVED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 28 FINAL MECHANICAL | ||
| Status | APPROVED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 29 FINAL PLUMBING | ||
| Status | APPROVED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 31 FINAL SITE | ||
| Status | APPROVED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 32 TEMPORARY ON-SITE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 33 LOWEST FLOOR | ||
| Status | APPROVED | |
| Last Scheduled | 03/24/2022 | |
| Last Inspected | 03/24/2022 | |
| 35 MISCELLANEOUS FOOTINGS | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 38 FENCE FTG | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 39 FENCE FINAL | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 40 RETAINING WALL FOOTING | ||
| Status | APPROVED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 41 RETAINING WALL FINAL | ||
| Status | APPROVED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 42 PRE SITE | ||
| Status | APPROVED | |
| Last Scheduled | 09/22/2020 | |
| Last Inspected | 09/22/2020 | |
| 43 FINAL OFFSITE PUBLIC WORKS | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 46 CONSTRUCTION MEETING | ||
| Status | APPROVED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 51 FIRE UNDERGROUND TEST ROUGH | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |
| 52 FIRE UNDERGROUND PRESSURE TEST | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 01/06/2023 | |
| Last Inspected | 01/06/2023 | |