Building Permit

Inspections cannot currently be scheduled for this permit (285665) because its status is set to "FINALLED" instead of "ACTIVE". Please contact support.
Permit Number
285665
Status
FINALLED
Issued
9/1/2022
Permit Type
SFR-CUSTOM IN SUBDIVISION
Zone
R1-7
Address
3505 N HOPI WY
Show on City Map
APN
130-05-056
Subdivision
SOUTHWEST VILLAGE UNIT THREE
Lot Size
9627 Sq Ft
Lot Number
294
Air Cond
4086 Sq Ft
Covered
783 Sq Ft
Fence
275 Ft
Owner
GREEN ELEPHANT DEVELOPMENT LLC
Responsible
GREEN ELEPHANT DEVELOPMENT LLC
Builder
GREEN ELEPHANT DEVELOPMENT LLC
Valuation
$587,804.12
3 FOOTING/EXTERIOR
Status APPROVED
Last Scheduled 09/27/2022
Last Inspected09/27/2022
4 STEM
Status APPROVED
Last Scheduled 10/07/2022
Last Inspected10/07/2022
5 PLUMBING/UNDERGROUND
Status APPROVED
Last Scheduled 10/13/2022
Last Inspected10/13/2022
6 FOOTING/INTERIOR
Status APPROVED
Last Scheduled 10/27/2022
Last Inspected10/27/2022
7 WATER/UNDERGROUND
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
8 WATER SERVICE
Status APPROVED
Last Scheduled 10/14/2022
Last Inspected10/14/2022
9 SEWER
Status APPROVED
Last Scheduled 12/21/2022
Last Inspected12/21/2022
10 ELECTRIC/UNDERGROUND
Status APPROVED
Last Scheduled 10/27/2022
Last Inspected10/27/2022
11 MASONRY GROUT
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
12 BOND BEAM
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
13 PUBLIC WORKS TEMPORARY C OF O
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
14 ROOF NAIL
Status APPROVED
Last Scheduled 01/20/2023
Last Inspected01/20/2023
15 ROUGH PLUMBING
Status APPROVED
Last Scheduled 04/24/2023
Last Inspected04/24/2023
16 ROUGH ELECTRIC
Status APPROVED
Last Scheduled 02/08/2023
Last Inspected02/08/2023
17 ROUGH MECHANICAL
Status APPROVED
Last Scheduled 02/08/2023
Last Inspected02/08/2023
18 ROUGH FRAME & INSULATION
Status APPROVED
Last Scheduled 02/15/2023
Last Inspected02/15/2023
19 WALLBOARD
Status APPROVED
Last Scheduled 03/15/2023
Last Inspected03/15/2023
20 EXTERIOR FOAM AND LATH
Status APPROVED
Last Scheduled 02/08/2023
Last Inspected02/08/2023
21 NATURAL GAS LINE
Status APPROVED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
22 PROPANE GAS LINE
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
24 TEMP ELEC/PERM POSITION
Status APPROVED
Last Scheduled 04/24/2023
Last Inspected04/24/2023
25 TEMP CERTIFICATE/OCCUPANCY
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
26 FINAL BUILDING
Status APPROVED
Last Scheduled 10/04/2023
Last Inspected10/04/2023
27 FINAL ELECTRIC
Status APPROVED
Last Scheduled 10/04/2023
Last Inspected10/04/2023
28 FINAL MECHANICAL
Status APPROVED
Last Scheduled 10/04/2023
Last Inspected10/04/2023
29 FINAL PLUMBING
Status APPROVED
Last Scheduled 09/19/2023
Last Inspected09/19/2023
31 FINAL SITE
Status APPROVED
Last Scheduled 10/04/2023
Last Inspected10/04/2023
32 TEMPORARY ON-SITE
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
33 LOWEST FLOOR
Status APPROVED
Last Scheduled 11/08/2022
Last Inspected11/07/2022
35 MISCELLANEOUS FOOTINGS
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
38 FENCE FTG
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
39 FENCE FINAL
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
40 RETAINING WALL FOOTING
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
41 RETAINING WALL FINAL
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
42 PRE SITE
Status APPROVED
Last Scheduled 09/02/2022
Last Inspected09/02/2022
43 FINAL OFFSITE PUBLIC WORKS
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
46 CONSTRUCTION MEETING
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
51 FIRE UNDERGROUND TEST ROUGH
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023
52 FIRE UNDERGROUND PRESSURE TEST
Status NOT REQUIRED
Last Scheduled 06/27/2023
Last Inspected06/27/2023