Building Permit
Inspections cannot currently be scheduled for this permit (290781) because its status is set to "FINALLED" instead of "ACTIVE". Please contact support.
Permit Number
290781
Status
FINALLED
Issued
2/13/2023
Permit Type
COMM REMODEL INT ONLY
Address
APN
212-34-959A
Subdivision
LOT 1A OF CAVASSON
Air Cond
12225 Sq Ft
Owner
NATIONWIDE REALITY INVESTORS - GREGORY J WILLIAMS
Responsible
NATIONWIDE REALITY INVESTORS - GREGORY J WILLIAMS
Builder
GCON INC
Valuation
$851,116.73
| 3 FOOTING/EXTERIOR | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 4 STEM | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 5 PLUMBING/UNDERGROUND | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 6 FOOTING/INTERIOR | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 7 WATER/UNDERGROUND | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 8 WATER SERVICE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 9 SEWER | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 10 ELECTRIC/UNDERGROUND | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 11 MASONRY GROUT | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 12 BOND BEAM | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 13 PUBLIC WORKS TEMPORARY C OF O | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 14 ROOF NAIL | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 15 ROUGH PLUMBING | ||
| Status | APPROVED | |
| Last Scheduled | 03/20/2023 | |
| Last Inspected | 03/20/2023 | |
| 16 ROUGH ELECTRIC | ||
| Status | APPROVED | |
| Last Scheduled | 04/21/2023 | |
| Last Inspected | 04/21/2023 | |
| 17 ROUGH MECHANICAL | ||
| Status | APPROVED | |
| Last Scheduled | 04/21/2023 | |
| Last Inspected | 04/21/2023 | |
| 18 ROUGH FRAME & INSULATION | ||
| Status | APPROVED | |
| Last Scheduled | 04/21/2023 | |
| Last Inspected | 04/21/2023 | |
| 19 WALLBOARD | ||
| Status | APPROVED | |
| Last Scheduled | 04/20/2023 | |
| Last Inspected | 04/20/2023 | |
| 20 EXTERIOR FOAM AND LATH | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 21 NATURAL GAS LINE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 22 PROPANE GAS LINE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 24 TEMP ELEC/PERM POSITION | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 25 TEMP CERTIFICATE/OCCUPANCY | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 26 FINAL BUILDING | ||
| Status | APPROVED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 27 FINAL ELECTRIC | ||
| Status | APPROVED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 28 FINAL MECHANICAL | ||
| Status | APPROVED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 29 FINAL PLUMBING | ||
| Status | APPROVED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 30 FINAL FIRE | ||
| Status | APPROVED | |
| Last Scheduled | 05/25/2023 | |
| Last Inspected | 05/25/2023 | |
| 31 FINAL SITE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 32 TEMPORARY ON-SITE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 33 LOWEST FLOOR | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 35 MISCELLANEOUS FOOTINGS | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 36 TEMP C/O FIRE INSPECTION | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 37 BACKFLOW | ||
| Status | APPROVED | |
| Last Scheduled | 04/21/2023 | |
| Last Inspected | 04/21/2023 | |
| 42 PRE SITE | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 43 FINAL OFFSITE PUBLIC WORKS | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 46 CONSTRUCTION MEETING | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 56 GREASE INTERCEPTOR | ||
| Status | NOT REQUIRED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |
| 110 RADIO AMPLIFICATION | ||
| Status | APPROVED | |
| Last Scheduled | 05/26/2023 | |
| Last Inspected | 05/26/2023 | |