Building Permit

Permit Number
300443
Status
ACTIVE
Issued
1/4/2024
Permit Type
SFR-ADDITION LESS 500 SQ FT
Zone
R1-70 ESL FO
Address
26833 N 78TH ST
Show on City Map
APN
212-22-048A
Lot Size
102702 Sq Ft
Air Cond
184 Sq Ft
Covered
623 Sq Ft
Fence
48 Ft
Owner
HANNAH JOAN WARDE TRUST
Responsible
DAVID DICK ARCHITECT
Builder
OWNER BUILDER
Valuation
$112,582.76
Login to Schedule

If you would like an estimated time of your inspection please call your inspector between 6:00 a.m. and 6:30 a.m. during our summer hours (Apr-Oct) or between 7:00 a.m. and 7:30 a.m. during our winter hours (Nov-Mar).

Route
8

Login
3 FOOTING/EXTERIOR
Status APPROVED
Last Scheduled 05/24/2024
Last Inspected05/24/2024
4 STEM
Status APPROVED
Last Scheduled 07/01/2024
Last Inspected07/01/2024
5 PLUMBING/UNDERGROUND
Status APPROVED
Last Scheduled 01/29/2024
Last Inspected01/29/2024
6 FOOTING/INTERIOR
7 WATER/UNDERGROUND
Status APPROVED
Last Scheduled 01/29/2024
Last Inspected01/29/2024
8 WATER SERVICE
9 SEWER
Status APPROVED
Last Scheduled 01/29/2024
Last Inspected01/29/2024
10 ELECTRIC/UNDERGROUND
11 MASONRY GROUT
Status APPROVED
Last Scheduled 07/25/2024
Last Inspected07/25/2024
12 BOND BEAM
Status APPROVED
Last Scheduled 07/25/2024
Last Inspected07/25/2024
14 ROOF NAIL
Status APPROVED
Last Scheduled 11/01/2024
Last Inspected11/01/2024
15 ROUGH PLUMBING
Status APPROVED
Last Scheduled 05/05/2025
Last Inspected05/05/2025
16 ROUGH ELECTRIC
Status APPROVED
Last Scheduled 01/21/2025
Last Inspected01/21/2025
17 ROUGH MECHANICAL
Status APPROVED
Last Scheduled 01/21/2025
Last Inspected01/21/2025
18 ROUGH FRAME & INSULATION
Status APPROVED
Last Scheduled 03/13/2025
Last Inspected03/13/2025
19 WALLBOARD
Status APPROVED
Last Scheduled 03/20/2025
Last Inspected03/20/2025
20 EXTERIOR FOAM AND LATH
21 NATURAL GAS LINE
22 PROPANE GAS LINE
Status PARTIAL
Last Scheduled 03/13/2025
Last Inspected03/13/2025
24 TEMP ELEC/PERM POSITION
25 TEMP CERTIFICATE/OCCUPANCY
26 FINAL BUILDING
27 FINAL ELECTRIC
Status PARTIAL
Last Scheduled 07/30/2024
Last Inspected07/30/2024
28 FINAL MECHANICAL
29 FINAL PLUMBING
31 FINAL SITE
32 TEMPORARY ON-SITE
33 LOWEST FLOOR
Status APPROVED
Last Scheduled 08/09/2024
Last Inspected08/08/2024
35 MISCELLANEOUS FOOTINGS
36 TEMP C/O FIRE INSPECTION
38 FENCE FTG
39 FENCE FINAL
40 RETAINING WALL FOOTING
41 RETAINING WALL FINAL
42 PRE SITE
Status APPROVED
Last Scheduled 01/18/2024
Last Inspected01/18/2024
43 FINAL OFFSITE PUBLIC WORKS
46 CONSTRUCTION MEETING
Status APPROVED
Last Scheduled 03/04/2024
Last Inspected03/04/2024